Chair of the FSD-PB PWI&E:
Tony Donné (EUROfusion Programme Manager)
Members of FSD-PB PWI&E:
Christian Linsmeier (FZJ)
Eduardo Alves (IST)
Elzbieta Fortuna-Zalesna (01-WUT)
Fulvio Militello (UKAEA)
Mihaela Ionescu-Bujor (KIT)
Philippe Magaud (CEA)
Wolfgang Jacob (MPG)
Thomas Morgan (DIFFER)
Paolo Innocente (ENEA)
Primoz Pelicon (JSI)
EUROfusion PMU:
Volker Naulin (FSD Head / E-TASC SB Chair)
Emilia Genangeli (Admin. Head)
Fabio Vinagre (PMO Head)
David Douai (FSD CO PWIE)
Denis Kalupin (FSD CO Theory and Modelling)
Sara Moradi (FSD CO Tokamak Exploitation)
Joao Figueiredo (FSD CO Enchancements)
Invited participants:
Sebastijan Brezinsek (FZJ / WP PWIE Leader)
Michael Reinhart (FZJ / WP PWIE PSO)
Richard Pitts (ITER IO)
Sebastijan Brezinsek presented the overview of WP PWIE activities
The Project Board members asked to clarify following points:
=> reflected in grant deliverables / ADC high priority to get soon an answer
=> criticial - no funding avaialble though ITER high priority. SP X2 address LIBS conditions as expected in ITER or JET (~0,95bar) and typical layer conditions
=> joint meeting of PL FSD/FTD biweekly, joint meeting of all FSD PL biweekly, SPL in WP WPWIE and SCs in WP TE are linked where appropriate
=> Thrusts as link to communicate / no direct impact of this PB /example MAGNUM experiments to study detachment feed into TSVV 5 as benchmark experiment
=> Volker Naulin: No overlapp as TSVV shall develop - no day to day modelling
=> WP PWIE for 2021 and 2022 almost fixed, other years resources indicativ. Changes according priority possible. Closure of TASKS e.g. KIT DIVGAS are foreseen
Denis Kalupin has presented the overview of EnR projects in the area of Materials:
PB members asked for clarifying the role of the PB in approval of EnR activities. T. Donné and V. Naulin have clarified that the main responsibility of the PB will be to follow the progress of EnR projects, check and approve necessary revisions to the EnR programme (following the recommendations of SB.EnR-MAT)
Since EnR projects have already been approved by the General Assembly, the PB agreed as an action to take a note on the project start.
In order to improove the communication on the ENR progress, PB recommended to have presentations by EnR PIs in EUROfusion Science Meeting or at the FSD Science Meeting.
T. Donné suggested organising the next Project Board Meeting in fall 2021.
The Project Board agreed that the 2nd 2021 Fusion Science Department Project Board – Plasma Wall Interactions and Exhaust will take place on 18th of November from 13:00 to 17:00 CET.